Awarded tenders
| Company | Description | Awarded | Amount |
|---|---|---|---|
| T.Y.LIN INTERNATIONAL PTE. LTD. | Provision of Consultancy Services for Feasibility Study on Infrastructure Works for Service Connectivity at Jurong Island | 2026-03-26 | S$432,500 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Sungei Kadut (Group 18) | 2026-03-25 | S$2,417,000 |
| KNIGHT FRANK PTE LTD | PROVISION OF RETAIL CONSULTANCY SERVICES PREDOMINANTLY FOR BUSINESS PARK / INDUSTRIAL B2 IN JURONG INNOVATION DISTRICT | 2026-03-19 | S$365,000 |
| AEQON TJ PTE. LTD. | PROVISION OF COMPREHENSIVE MAINTENANCE FOR NON-PROPRIETARY SYSTEMS AT JI CHECKPOINT & PDL CHECKPOINT FOR PERIOD OF 2 YEARS | 2026-02-27 | S$455,112 |
| EASE SOLUTIONS PTE. LTD. Not yet published | PROVISION OF JIRA SERVICE MANAGEMENT (DATA CENTER) AND PLUGINS SUBSCRIPTION WITH MAINTENANCE FOR JTC | 2026-02-11 | S$197,271 |
| LSW CONSULTING ENGINEERS PTE. LTD. Not yet published | Provision of Civil & Structural Engineering Consultancy Services for Infrastructure Works at East Seletar | 2026-01-29 | S$1,982,008.74 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | PROPOSED DEMOLITION OF EXISTING FACTORY BUILDINGS AND ANCILLARY STRUCTURES AT KRANJI WAY, SUNGEI KADUT AND TUAS (GROUP 17) | 2026-01-21 | S$2,674,000 |
| AUTOMATIC CONTROLS AND INSTRUMENTATION PTE. LTD. | DESIGN, SUPPLY, INSTALL, TEST AND COMMISSION OPEN DIGITAL PLATFORM (ODP) INTERFACE MODULES FOR LIFT INTEGRATION TO THE ODP AT BULIM SQUARE | 2026-01-19 | S$34,200 |
| ACEPLP.COM PTE LTD Not yet published | 2-YEAR TERM CONTRACT FOR PROVISION OF THREE (3) IN-SOURCED IDD MANAGERS AND TWO (2) EXECUTIVE ADMINISTRATORS FOR MANAGEMENT OF BUILT ENVIRONMENT (BE) PROJECTS AND CDE ADMINISTRATIVE MATTERS | 2026-01-19 | S$1,593,600 |
| DELOITTE SINGAPORE ASSURANCE PTE. LTD. | Provision Of Consultancy Services On Audit Methodology & Benchmarking For Audit & Advisory Division (AAD) | 2026-01-02 | S$332,400 |
| SOIL INVESTIGATION PTE. LIMITED | Instrument Monitoring Works for Proposed Reclamation at Northern Tuas Basin | 2025-12-19 | S$1,999,000 |
| HTC SOFTWARE SINGAPORE PTE LTD | Provision of Contract Resources for Finance Operations in JTC | 2025-12-19 | S$1 |
| RMA CONTRACTS PTE. LTD. | Provision of Contract Resources for Finance Operations in JTC | 2025-12-19 | S$1 |
| EXPERTISE TECHNOLOGIES PTE LTD | Provision of Contract Resources for Finance Operations in JTC | 2025-12-19 | S$1 |
| MORGAN MCKINLEY PTE. LTD. | Provision of Contract Resources for Finance Operations in JTC | 2025-12-19 | S$1 |
| STEADFAST ENGINEERING & CONSTRUCTION PTE. LTD. Not yet published | REPAIR OF 20 JURONG PIER ROAD BUILDING UNDERDECK AND DEMOLITION OF EXISTING JETTY (PIER 20) AT 35 JURONG PIER ROAD | 2025-12-19 | S$2,758,210 |
| ASCENDION ENGINEERING SOLUTIONS SINGAPORE PTE. LTD. Not yet published | Provision of Contract Resources for Finance Operations in JTC | 2025-12-19 | S$1 |
| WSH EXPERTS PTE. LTD. Not yet published | Provision of Contract Resources for Finance Operations in JTC | 2025-12-19 | S$1 |
| HWEE WAH ENGINEERING PTE. LTD. | Proposed Land Rectification Works at Kaki Bukit iGLS along Bedok Reservoir Road | 2025-12-11 | S$3,000,000 |
| MIE-TECH ENGINEERING & CONSTRUCTION PTE LTD | PROPOSED REPAIRS AND REFURBISHMENTS OF UNITS #01-1367, 1369 & 1375 WITH RECONSTRUCTION OF UNITS #01-1371 & 1373 OF BLOCK 3 ON LOT 10841P MK 17 @ TOA PAYOH INDUSTRIAL PARK | 2025-12-10 | S$647,700 |
| HUATIONG CONTRACTOR PTE LTD | Proposed Development of Heavy Vehicle Park at Tengah | 2025-11-27 | S$22,380,000 |
| AECOM SINGAPORE PTE. LTD. | Provision of Multi-Disciplinary Consultancy Services for Preliminary Coastal Development Plan at West of Singapore | 2025-11-24 | S$4,200,001 |
| NEXUS CONSULTANCY SERVICES PTE LTD | 3-YEAR TERM CONTRACT FOR LEASING OF CONTAINER OFFICES AT JURONG ISLAND CHECKPOINT | 2025-11-20 | S$217,300 |
| P & T CONSULTANTS PTE. LTD. | Multi-Disciplinary Consultancy Services for JTC Food Hub 2 @ Senoko | 2025-11-18 | S$180,003.57 |
| HAO DA PTE LTD | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| BENG SOON MACHINERY SERVICES (SINGAPORE) PTE LTD | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| BENG HENG ENGINEERING PTE LTD | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| KTC CIVIL ENGINEERING & CONSTRUCTION PTE LTD | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| HWA AIK ENGINEERING PTE. LTD. | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| RECLAIMS ENTERPRISE PTE. LTD. | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| HI-TACT SOLUTIONS & TRADING PTE. LTD. | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| YONGSHENG E & C PTE. LTD. Not yet published | PREQUALIFICATION OF CONTRACTORS FOR LISTING ON JTC'S PANEL OF DEMOLITION CONTRACTORS FOR A PERIOD OF 3 + 2 YEARS | 2025-11-03 | S$1 |
| QXY RESOURCES PTE. LTD. | Outstanding Works and Defects Rectification at CleanTech Three, CleanTech Loop | 2025-10-28 | S$3,879,000 |
| MEINHARDT (SINGAPORE) PTE LTD | ACCREDITED CHECKING ORGANISATION (ACO) AND SPECIALIST ACCREDITED CHECKERS (GEOTECHNICAL) [AC(GEO)] PROFESSIONAL SERVICES FOR PROPOSED RECLAMATION AT NORTHERN TUAS BASIN | 2025-10-27 | S$1,180,500 |
| GLOBAL SINOTRUST PTE. LTD. | INSTRUMENTATION AND MONITORING WORK FOR PROPOSED ROADS, DRAINS AND SEWERS AT LOYANG WAY AND LOYANG HEIGHTS | 2025-10-27 | S$82,687 |
| FREIGHT LINKS EXPRESS ARCHIVERS PTE LTD | PROVISION OF STORAGE AND RECORDS MANAGEMENT SERVICES FOR 3 CALENDAR YEARS | 2025-10-13 | S$221,529.5 |
| ENVIRONMENTAL RESOURCES MANAGEMENT (S) PTE LTD Not yet published | Consultancy Studies of Net Zero Emission Zones, JTC's Carbon Emission Profile and Decarbonization Roadmap | 2025-10-07 | S$490,813 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | PROPOSED DEMOLITION OF EXISTING FACTORY BUILDINGS AND ANCILLARY STRUCTURES AT DEFU LANE AND KALLANG WAY (GROUP 14) | 2025-10-02 | S$2,989,000 |
| R.J. CROCKER CONSULTANTS PTE. LTD. | 2+2 YEARS TERM CONTRACT FOR PROVISION OF WORKPLACE SAFETY AND HEALTH PROFESSIONALS | 2025-10-01 | S$26,798 |
| ENG LAM CONTRACTORS CO (PTE) LTD | Construction of Infrastructure Works at Cleantech Loop (Phase 2A) | 2025-10-01 | S$22,638,000 |
| GREENSAFE INTERNATIONAL PTE. LTD. | 2+2 YEARS TERM CONTRACT FOR PROVISION OF WORKPLACE SAFETY AND HEALTH PROFESSIONALS | 2025-10-01 | S$21,100 |
| SHINGDA CONSTRUCTION PTE. LTD. | Proposed NEWater Pipe Diversion Works at Ang Mo Kio Industrial Park 2 | 2025-09-19 | S$5,235,265 |
| FLEMINGS SAFETY PTE. LTD. | 2 YEAR TERM CONTRACT FOR THE SUPPLY OF PERSONNEL PROTECTIVE EQUIPMENT (PPE) TO JTC STAFF | 2025-09-10 | S$1 |
| HELM MARINE (SINGAPORE) PTE. LTD. Not yet published | APPOINTMENT OF CONTRACTOR FOR THE MAINTENANCE OF NAVIGATIONAL AIDS AT TUAS BAY FOR TWO (2) YEARS | 2025-09-06 | S$223,632 |
| HWA AIK ENGINEERING PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Link Road, Senoko Drive & Senoko Loop (Group 12) | 2025-09-02 | S$2,120,000 |
| KLERRA PTE. LTD. Not yet published | Challenge Statement - Data-led Mixed Use Waste Handling | 2025-08-29 | S$432,383 |
| ENVIRONMENTAL RESOURCES MANAGEMENT (S) PTE LTD Not yet published | ENGAGEMENT OF CONSULTANCY SERVICES TO CARRY OUT RISK ASSESSMENT FOR DATA CENTRE SITING ON JURONG ISLAND | 2025-08-28 | S$168,000 |
| ECAS CONSULTANTS PTE. LTD. | Accredited Checking Services for Roads, Drains and Sewer Works at Loyang Way | 2025-08-15 | S$211,000 |
| LEAP INTEGRATED PTE. LTD. | Proposed upscaling works for ACMV and Electrical System at JTC Cleantech 3 @ CleanTech Park | 2025-08-12 | S$5,746,816 |
| BENG SOON MACHINERY SERVICES (SINGAPORE) PTE LTD | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Jalan Ahmad Ibrahim, Tanjong Penjuru and Defu Industrial Park (Group 13) | 2025-08-11 | S$4,223,000 |
| ARUP SINGAPORE PRIVATE LIMITED | Multi-Disciplinary Consultancy Services for Feasibility Study for Solar Canopies Deployment | 2025-08-01 | S$3,880,000 |
| NEO & GOH CONSTRUCTION PTE LTD | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Defu Industrial Park (Batch 3) | 2025-07-04 | S$2,760,000 |
| QXY RESOURCES PTE. LTD. | DESIGN & BUILD FOR REVAMP OF THE MEETING POINT AT LAUNCHPAD AT ONE-NORTH | 2025-07-04 | S$1,188,000 |
| PENTA-OCEAN CONSTRUCTION COMPANY LIMITED | PROPOSED RECLAMATION AT NORTHERN TUAS BASIN | 2025-06-30 | S$299,500,000 |
| ACEPLP.COM PTE LTD Not yet published | ENGAGEMENT OF SERVICES FOR 2D TO 3D MODEL CONSTRUCTION PROJECT | 2025-06-30 | S$514,510 |
| BIMAGE CONSULTING PTE. LTD. Not yet published | ENGAGEMENT OF SERVICES FOR 2D TO 3D MODEL CONSTRUCTION PROJECT | 2025-06-30 | S$546,000 |
| KPMG SERVICES PTE. LTD. | Provision of Application Management Services for Finance, Projects and Procurement (SAP) and Related Applications for JTC Corporation | 2025-06-17 | S$2,999,673 |
| GEONAMICS (S) PTE LTD | Soil Investigation and Survey Works at West Jurong Channel | 2025-06-06 | S$1,676,619 |
| BDO CONSULTANTS PTE. LTD. | PROVISION OF SUSTAINABILITY REPORTING CONSULTANCY SERVICES FOR JTC CORPORATION | 2025-06-04 | S$48,000 |
| QXY RESOURCES PTE. LTD. | Improvement Works to High Rise Multi-User Industrial Complex (DIC) at 2 Defu South Street 1 | 2025-05-08 | S$4,753,000 |
| JANGHO CURTAIN WALL SINGAPORE PTE. LTD. | Proposed Facade Recladding to Block 7 (Helios) of Biopolis on Lot 04932W Mukim 3 at North Buona Vista Drive (Queenstown Planning Area) | 2025-04-29 | S$24,062,876 |
| ELEMENT GEOTECHNICAL TESTING (S) PTE. LTD. | Instrumentation and Monitoring Works for Slopes 2, 4, 6 and 7 at Jurong Hill | 2025-04-17 | S$74,640 |
| AIK SAN CONSTRUCTION PTE LTD | REPLACEMENT OF WATERPROOFING SYSTEM IN REVENUE HOUSE AND THE TREASURY | 2025-04-02 | S$5,032,000 |
| NDI AUTOMATION PTE. LTD. Not yet published | Provision of Specialist Consultancy Services for Proposed Electronic Overhead Travelling Cranes at JTC Logistics Hub @ Gul | 2025-04-02 | S$247,500 |
| WOODLANDS TRANSPORT SERVICE PTE LTD | Provision of Shuttle Bus Services at Jurong Island for 2 Years | 2025-03-28 | S$1,433,280 |
| TONG TAR TRANSPORT SERVICE PTE LTD | Provision of Shuttle Bus Services at Jurong Island for 2 Years | 2025-03-28 | S$2,832,000 |
| D' PERCEPTION SINGAPORE PTE. LTD. | Interior Fit-out Works to Level 21 at the JTC Summit Office Building | 2025-03-25 | S$2,153,184.43 |
| QBE INSURANCE (SINGAPORE) PTE. LTD. | PLACEMENT OF INSURANCE POLICIES FOR JTC's CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS WITH OPTION TO EXTEND FOR 1 YEAR | 2025-03-21 | S$1 |
| SOMPO INSURANCE SINGAPORE PTE. LTD. | PLACEMENT OF INSURANCE POLICIES FOR JTC's CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS WITH OPTION TO EXTEND FOR 1 YEAR | 2025-03-21 | S$1 |
| MS FIRST CAPITAL INSURANCE LIMITED | PLACEMENT OF INSURANCE POLICIES FOR JTC's CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS WITH OPTION TO EXTEND FOR 1 YEAR | 2025-03-21 | S$1 |
| CHUBB INSURANCE SINGAPORE LIMITED | PLACEMENT OF INSURANCE POLICIES FOR JTC's CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS WITH OPTION TO EXTEND FOR 1 YEAR | 2025-03-21 | S$1 |
| INDIA INTERNATIONAL INSURANCE PTE LTD Not yet published | PLACEMENT OF INSURANCE POLICIES FOR JTC's CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS WITH OPTION TO EXTEND FOR 1 YEAR | 2025-03-21 | S$1 |
| LIBERTY PTE. LIMITED Not yet published | PLACEMENT OF INSURANCE POLICIES FOR JTC's CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS WITH OPTION TO EXTEND FOR 1 YEAR | 2025-03-21 | S$1 |
| BUREAU VERITAS BUILDINGS & INFRASTRUCTURE PTE. LTD. | 2+1 YEAR TERM CONTRACT FOR PROVISION OF RESIDENT SITE SUPERVISORS FOR JTC'S BUILDING AND INFRASTRUCTURE PROJECTS (YEAR 2025 to 2027) | 2025-03-14 | S$30,300 |
| AIS-HILL PTE. LTD. | 2+1+1 Year Term Contract for Provision of Project Managers for Management of Various Infrastructure and Building Projects | 2025-03-13 | S$4 |
| EASE SOLUTIONS PTE. LTD. Not yet published | PROVISION OF JIRA SERVICE MANAGEMENT (DATA CENTER) AND PLUGINS SUBSCRIPTION WITH MAINTENANCE FOR JTC | 2025-03-05 | S$166,658.84 |
| HPC BUILDERS PTE. LTD. | Design Development and Build for Additions & Alterations to Existing 4-Storey Multi-User Cleanroom Industrial Development with Ancillary Facilities and Demolition & Construction of 3-Storey Central Utility Building for 11 Tampines Industrial Crescent | 2025-02-25 | S$188,800,000 |
| EVVO LABS PTE. LTD. Not yet published | Provision of Security Rating Services Subscription | 2025-02-11 | S$22,632 |
| VIVATA PTE. LTD. | Provision of Multi-Disciplinary Consultancy Services for Improvement Works at JTC Logistics Hub (JLH), Kranji Green (KG) and Timmac | 2025-01-08 | S$13.56 |
| AEQON TJ PTE. LTD. | Provision of Jurong Island (JI) CCTV Enhancement for 3 Years | 2024-12-30 | S$2,062,000 |
| CTC GLOBAL PTE. LTD. | Provision of MongoDB Software Licenses Subscription Renewal and Professional Services for JTC Datahub | 2024-12-30 | S$313,404.12 |
| SURBANA JURONG CONSULTANTS PTE. LTD. | Multi-Disciplinary Consultancy Services for the Shoreline Stabilisation at Tuas Curve Profile | 2024-12-27 | S$8,737,701 |
| UTRACO PTE. LTD. | Permanent Slope Repair and Strengthening Works to Slope 2, 4, 6 and 7 and Ancillary Works at Jurong Hill. | 2024-12-26 | S$5,988,800 |
| SCAL ACADEMY PTE. LTD. Not yet published | 3 YEAR TERM CONTRACT FOR THE DESIGN, BUILD AND MAINTAIN THE CONSTRUCTION SAFETY SCHOOL AT JTC SPACE@GUL | 2024-12-12 | S$1 |
| ENTIIS PTE. LTD. | PROVISION OF PRIVILEGE ACTIVITY RECORDING SYSTEM (OBSERVEIT) SOFTWARE LICENSING SUPPORT AND MAINTENANCE FOR A PERIOD OF 1 YEAR | 2024-12-05 | S$72,000 |
| DP ARCHITECTS PTE LTD. Not yet published | Provision Of Multi-Disciplinary Consultancy Services for Proposed Development of 66kV Substation at Ang Mo Kio | 2024-11-29 | S$16.92 |
| PRICEWATERHOUSECOOPERS RISK SERVICES PTE. LTD. | CONSULTANCY TO REVIEW AND PROPOSE ENHANCEMENTS TO JTC CORPORATION'S BUSINESS RESILIENCE GROUP | 2024-11-26 | S$140,160 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | Proposed Demolition of Existing Factory Building and Ancillary Structures at Gul Circle, Kranji Way, Sungei Kadut and Penjuru Road | 2024-11-22 | S$5,594,000 |
| K.C. DAT (SINGAPORE) PRIVATE LIMITED | Tender for Appointment of Contractor for the Provision of Packing, Moving and Storage Services for Three (3) Office Buildings at Orchard Road | 2024-11-20 | S$630,242 |
| SUNRAY WOODCRAFT CONSTRUCTION PTE LTD | Proposed Addition and Alteration Works and Restoration Works to Two (2) Conservation Buildings and One (1) Three-Storey Building at Orchard Road. | 2024-11-07 | S$142,388,889 |
| S K E ENGINEERING (S) PTE LTD | Repair and Reinstatement Works to Fire Affected Bus-Ducts at Level 1 and 2 of Block 3023 UbiPlex 1, Ubi Road 3 | 2024-11-05 | S$155,500 |
| BAN CHON CORPORATION & TRADING PTE LTD | PROPOSED ROAD WIDENING AND SEWER & DRAIN UPGRADING WORKS AT KOLAM AYER INDUSTRIAL ESTATE | 2024-11-05 | S$24,981,216 |
| WILSON PARKING (SINGAPORE) PTE. LTD. | IMPLEMENTATION OF SEASON SALE SYSTEM FOR JTC'S GAZETTED CARPARKS FOR A PERIOD OF 3+1+1 YEARS | 2024-11-04 | S$218,000 |
| TOKIO MARINE INSURANCE SINGAPORE LTD. | PROVISION OF WORK INJURY COMPENSATION, GROUP PERSONAL ACCIDENT AND GROUP TERM LIFE INSURANCE PROGRAMME FOR 2 YEARS | 2024-10-28 | S$1 |
| THE GREAT EASTERN LIFE ASSURANCE COMPANY LIMITED Not yet published | PROVISION OF WORK INJURY COMPENSATION, GROUP PERSONAL ACCIDENT AND GROUP TERM LIFE INSURANCE PROGRAMME FOR 2 YEARS | 2024-10-28 | S$1 |
| ZURICH INSURANCE COMPANY LTD (Singapore Branch) Not yet published | PROVISION OF WORK INJURY COMPENSATION, GROUP PERSONAL ACCIDENT AND GROUP TERM LIFE INSURANCE PROGRAMME FOR 2 YEARS | 2024-10-28 | S$1 |
| CHARTWORTH ENTERPRISE SINGAPORE PTE. LTD. | CONSTRUCTION OF BACKUP SEWER CROSSINGS AT MERANTI CRESCENT, JURONG ISLAND | 2024-10-25 | S$6,867,538 |
| ECAS CONSULTANTS PTE. LTD. | ACCREDITED CHECKING ORGANISATION (ACO) AND SPECIALIST ACCREDITED CHECKING (GEOTECHNICAL) SERVICES FOR PROPOSED COASTAL DEVELOPMENT | 2024-10-25 | S$460,050 |
| RYOBI GEOTECHNIQUE INTERNATIONAL PTE. LTD. | INSTRUMENT MONITORING WORKS FOR PROPOSED COASTAL DEVELOPMENT | 2024-10-24 | S$2,170,000 |
| CHBC INTEGRATED BUILDERS PTE. LTD. | PROVISION OF RESOURCES TO CARRY OUT INSPECTION TO PREMISES FOR A PERIOD OF 3 YEARS | 2024-10-21 | S$1,297,008 |
| WSH EXPERTS PTE. LTD. Not yet published | PROVISION OF RESOURCES TO CARRY OUT INSPECTION TO PREMISES FOR A PERIOD OF 3 YEARS | 2024-10-21 | S$1,828,800 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | Proposed Demolition of Existing Factory Building and Ancillary Structures at Tuas Basin Close, Tuas Crescent, Tuas Basin Link, Tuas Basin Lane, Tuas Road & Tuas South Avenue 5 | 2024-10-18 | S$2,950,000 |
| SERVICE CONNECTIONS HR CONSULTANCY PTE. LTD. Not yet published | 1 + 1 YEAR TERM CONTRACT FOR PROVISION OF ONE ADMINISTRATIVE EXECUTIVE (AE) | 2024-10-15 | S$37,884 |
| VISUALMEDIAWORKS PTE LTD | PROVISION OF VIDEO PRODUCTION AND 3D ANIMATION SERVICES FOR JURONG INNOVATION DISTRICT | 2024-10-14 | S$175,000 |
| WSH EXPERTS PTE. LTD. Not yet published | Provision of Site Supervision Staff for JTC Reclamation and Marine Related Projects | 2024-10-11 | S$48,240 |
| ELEMENT GEOTECHNICAL TESTING (S) PTE. LTD. | Instrumentation and Monitoring Works for Bulim Phase 2 Infrastructure | 2024-10-01 | S$747,781.97 |
| CPG CONSULTANTS PTE LTD | 3-Year TC for Provision of Consultancy Services for Traffic Impact Assessment (TIA) Studies for JTC's Developments and Industrial Estates | 2024-09-26 | S$1 |
| SYSTRA MVA SINGAPORE PTE. LTD. | 3-Year TC for Provision of Consultancy Services for Traffic Impact Assessment (TIA) Studies for JTC's Developments and Industrial Estates | 2024-09-26 | S$1 |
| KIM YEW INTEGRATED PTE. LTD. | APPOINTMENT OF INTEGRATED BUILDING CONTRACTOR (IBC) TO GOVERNMENT BUILDINGS ALONG ORCHARD ROAD FOR A PERIOD OF 3 YEARS | 2024-09-09 | S$7,369,566 |
| STARHUB LTD. | INVITATION TO TENDER FOR OPEN DIGITAL PLATFORM (ODP) INFRASTRUCTURE | 2024-09-06 | S$2,423,504 |
| BIMFINITY INTERNATIONAL PTE. LTD. Not yet published | 1-Year Term Contract for Provision of One (1) Civil and Structural Engineer and One (1) Mechanical BIM Engineer/Modeller for JTC Projects | 2024-09-03 | S$87,600 |
| WSH EXPERTS PTE. LTD. Not yet published | 1-Year Term Contract for Provision of One (1) Civil and Structural Engineer and One (1) Mechanical BIM Engineer/Modeller for JTC Projects | 2024-09-03 | S$110,040 |
| CBRE PTE. LTD. | Engagement of Consultancy Services for International (Industrial Land) Benchmarking Study | 2024-08-30 | S$1 |
| MS FIRST CAPITAL INSURANCE LIMITED | PLACEMENT OF INSURANCE POLICIES FOR THE OPERATION OF JURONG ROCK CAVERNS FOR A PERIOD OF 18 MONTHS WITH AN OPTION TO EXTEND FOR ANOTHER 18 MONTHS | 2024-08-29 | S$1 |
| KPMG SERVICES PTE. LTD. | Renewal Of Incident Response Retainer Services | 2024-08-28 | S$112,500 |
| TRENDBUILD CONTRACTS PTE. LTD. | Supply and installation of Fitting Out, Furnishing and Loose Furniture at Punggol Digital District | 2024-08-28 | S$1,395,800 |
| INTERLOCK SECURITY AND INVESTIGATION SERVICES PTE LTD | JTC Innovation Challenge 2023: Challenge Statement 3 -Solutions to inspect and effectively clear choked drain pipes in buildings | 2024-08-26 | S$250,000 |
| OTN BUILDING COST CONSULTANTS PTE. LTD. | 2+1 YEAR TERM QUANTITY SURVEYING CONSULTANCY SERVICES FOR PROPOSED DEMOLITION OF EXISTING JTC FACTORY BUILDINGS AND ANCILLARY STRUCTURES | 2024-08-20 | S$5 |
| CSN CONSULTANTS PTE. LTD. Not yet published | 2+1 YEAR TERM QUANTITY SURVEYING CONSULTANCY SERVICES FOR PROPOSED DEMOLITION OF EXISTING JTC FACTORY BUILDINGS AND ANCILLARY STRUCTURES | 2024-08-20 | S$3 |
| DBS BANK LTD. | Consultancy Service to Review and Make Recommendations on the Optimisation of JTC's Property Portfolio | 2024-08-14 | S$1 |
| CBRE GWS PTE. LTD. | APPOINTMENT OF FMC FOR FACILITIES MAINTENANCE OF CSC FOR A PERIOD OF 3 YEARS | 2024-08-13 | S$7,424,002.92 |
| DP ARCHITECTS PTE LTD. Not yet published | Multi-Disciplinary Consultancy Services for Building Study and Analysis of 10 View Road and Surrounding Area | 2024-08-08 | S$2,954,361 |
| VIGCON CONSTRUCTION PTE LTD | PROPOSED ADDITION & ALTERATION WORKS TO EXISTING 8 STOREY FLATTED FACTORY (WITH 1 LEVEL BASEMENT CARPARK) AT AYER RAJAH CRESCENT/ AYER RAJAH AVENUE ON LOT 5364N MK03 (QUEENSTOWN PLANNING AREA) | 2024-08-01 | S$27,375,000 |
| WSP CONSULTANCY PTE. LTD. | JTC's Independent Civil and Structural Consultancy Panel on Infrastructure Projects for a period of 2+1+1 years | 2024-07-30 | S$4 |
| AIS-HILL PTE. LTD. | JTC's Independent Civil and Structural Consultancy Panel on Infrastructure Projects for a period of 2+1+1 years | 2024-07-30 | S$2 |
| CPG CONSULTANTS PTE LTD | JTC's Independent Civil and Structural Consultancy Panel on Infrastructure Projects for a period of 2+1+1 years | 2024-07-30 | S$4 |
| LSW CONSULTING ENGINEERS PTE. LTD. Not yet published | JTC's Independent Civil and Structural Consultancy Panel on Infrastructure Projects for a period of 2+1+1 years | 2024-07-30 | S$4 |
| JIB SPECIALIST CONSULTANTS PTE. LTD. Not yet published | JTC's Independent Civil and Structural Consultancy Panel on Infrastructure Projects for a period of 2+1+1 years | 2024-07-30 | S$2 |
| HARVEST CONSULTING ENGINEERS LLP Not yet published | JTC's Independent Civil and Structural Consultancy Panel on Infrastructure Projects for a period of 2+1+1 years | 2024-07-30 | S$2 |
| NCS PTE. LTD. | Provision of Maintenance Contract for IT Equipment | 2024-07-29 | S$2,206,796 |
| KTC CIVIL ENGINEERING & CONSTRUCTION PTE LTD | Construction of Infrastructure Works at Bulim (Phase 2) | 2024-07-22 | S$617,768,000 |
| WSH EXPERTS PTE. LTD. Not yet published | Provision Of Professionals and Executives for JTC New Estates Developments | 2024-07-16 | S$2 |
| DELOITTE SINGAPORE ASSURANCE PTE. LTD. | PROVISION OF INTERNAL AUDIT SERVICES FOR 2 YEARS | 2024-07-05 | S$888,000 |
| SURBANA TECHNOLOGIES PTE. LTD. | Provision of Smart Building Solutions Study and Advisory Services | 2024-07-01 | S$41,400 |
| BAN CHON CORPORATION & TRADING PTE LTD | Sewer Upgrading Along Tuas View Crescent | 2024-06-20 | S$7,382,680 |
| CTM FACILITIES MANAGEMENT PTE. LTD. | APPOINTMENT OF FACILITY MANAGEMENT COMPANY FOR FACILITIES MAINTENANCE OF JTC NANOSPACE @ TAMPINES FOR A PERIOD OF 2 YEARS | 2024-06-14 | S$5,992,532.99 |
| HUATIONG CONTRACTOR PTE LTD | Design and Construction of Cul-De-Sac Road and Associated Infrastructure Works at Pasir Ris Wafer Fab Park | 2024-06-14 | S$9,678,800 |
| ENTIIS PTE. LTD. | SOFTWARE LICENSE MAINTENANCE RENEWAL OF CA WORKLOAD AUTOMATION | 2024-06-10 | S$483,400 |
| NCS PTE. LTD. | Renewal of eG Monitoring Software and Maintenance Licensing for 5 years | 2024-05-31 | S$269,340 |
| AEDGE HOLDINGS PTE. LTD. | 2-Year Term Contract for the Provision of Shuttle Bus Services at Seletar Aerospace Park and CleanTech Park | 2024-05-31 | S$1,223,376 |
| LEISURE FRONTIER (S) PTE. LTD. Not yet published | 2-YEAR TERM CONTRACT FOR THE PROVISION OF SHUTTLE BUS SERVICE AT AIRPORT LOGISTICS PARK OF SINGAPORE | 2024-05-31 | S$228,000 |
| KPMG SERVICES PTE. LTD. | PROFESSIONAL SERVICES FOR THE IMPLEMENTATION AND SYSTEM OPERATION SUPPORT SERVICES OF CUSTOMER RELATIONSHIP MANAGEMENT (CRM) | 2024-05-23 | S$2,933,005.41 |
| SOIL INVESTIGATION PTE. LIMITED | 2-Year Term Contract for Geophysical and Survey Works for JTC Estates | 2024-05-15 | S$1 |
| CAST LABORATORIES PTE LTD | 2-Year Term Contract for Soil Investigation Works Within JTC Estate | 2024-05-15 | S$1 |
| RYOBI GEOTECHNIQUE INTERNATIONAL PTE. LTD. | 2-Year Term Contract for Soil Investigation Works Within JTC Estate | 2024-05-15 | S$1 |
| RYOBI GEOTECHNIQUE INTERNATIONAL PTE. LTD. | 2-Year Term Contract for Geophysical and Survey Works for JTC Estates | 2024-05-15 | S$1 |
| DP ARCHITECTS PTE LTD. Not yet published | Provision of Multi-Disciplinary Consultancy Services for Proposed JTC Space @ AMK 2 | 2024-04-30 | S$4.41 |
| CSK LANDSCAPE SERVICES (S) PTE. LTD. | Provision of certified arborists and manpower to support the Master Landscape Services Contract for JTC Parks and Gardens and other landscape implementation projects. | 2024-04-29 | S$947,750 |
| ST ENGINEERING MISSION SOFTWARE & SERVICES PTE. LTD. | JTC Innovation Challenge 2023: Challenge Statement 1 - Improving security surveillance, situational awareness and incident response in JTC's industrial estates | 2024-04-26 | S$248,000 |
| AECOM SINGAPORE PTE. LTD. | 24 Months Term Contract for Provision of Environmental Advisory Services (Year 2024 - Year 2026) | 2024-04-18 | S$722,100 |
| TURNER & TOWNSEND PTE. LIMITED | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$12 |
| OTN BUILDING COST CONSULTANTS PTE. LTD. | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$5 |
| AECOM COST CONSULTING AND PROJECT MANAGEMENT (SINGAPORE) PTE. LTD. | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$10 |
| ASIA INFRASTRUCTURE SOLUTIONS SINGAPORE PTE. LTD. | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$10 |
| DK OUTSOURCE PTE. LTD. Not yet published | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$2 |
| PQS CONSULTANTS PTE. LTD. Not yet published | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$4 |
| QS CONSULTANTS PTE. LTD. Not yet published | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$2 |
| CSN CONSULTANTS PTE. LTD. Not yet published | JTC's Independent Quantity Surveying Consultancy Panel for a Period of 2 + 1 + 1 Years | 2024-04-18 | S$1 |
| CHARTWORTH ENTERPRISE SINGAPORE PTE. LTD. | Proposed Infrastructure Works at Ayer Merbau Road, Jurong Island | 2024-04-09 | S$15,929,438 |
| CTM FACILITIES MANAGEMENT PTE. LTD. | APPOINTMENT OF FMC FOR FACILITIES MAINTENANCE OF JURONG ISLAND PROPERTIES AND ESTATES FOR A PERIOD OF 3 YEARS | 2024-04-03 | S$20,545,099.72 |
| MAO SHENG QUANJI CONSTRUCTION PTE LTD | Master Landscape Services Contract for JTC Properties and Estates | 2024-04-03 | S$5,866,467 |
| VIGCON CONSTRUCTION PTE LTD | Proposed Regularisation of Fire Safety Works to Existing Fusionopolis One Building on Lot 04044T MK 03 at 1/3 Fusionopolis Way | 2024-04-03 | S$10,556,500 |
| WOODLANDS TRANSPORT SERVICE PTE LTD | 2-Year Term Contract for the Provision of Shuttle Bus Services at International Business Park | 2024-03-27 | S$441,600 |
| RECLAIMS ENTERPRISE PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Defu Industrial Park (Batch 2) | 2024-03-22 | S$1,600,000 |
| FONG CONSULT PTE. LTD. Not yet published | PERIODIC STRUCTURAL INSPECTION WORKS AT JTC INDUSTRIAL PROPERTIES IN EAST DIVISION | 2024-03-22 | S$49,100 |
| XLT SYSTEMS PTE. LTD. Not yet published | ENGAGEMENT OF SERVICES FOR AUDIO-VISUAL AND VIDEO CONFERENCING SYSTEM ENHANCEMENT WORKS FOR MINISTRY OF COMMUNICATIONS AND INFORMATION (MCI) AT OLD HILL STREET POLICE STATION LEVEL 1 COLLABORATION ROOMS AND BASEMENT 2 SITUATION OFFICE | 2024-03-21 | S$205,580 |
| SHENGJIE ENGINEERING PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Defu Lane and Attap Valley | 2024-03-20 | S$3,400,000 |
| BIMAGE CONSULTING PTE. LTD. Not yet published | IFC VIEWER TRAINING FOR JTC EPIC PROCESSING AND COMMENTING OFFICERS | 2024-02-29 | S$39,600 |
| EASE SOLUTIONS PTE. LTD. Not yet published | Provision of JIRA Service Management (Data Center) and Plugins Subscription with Maintenance for JTC | 2024-02-29 | S$148,750.75 |
| NCS PTE. LTD. | Engagement of Robotics Food Delivery Services | 2024-02-23 | S$132,679 |
| KJS CONSTRUCTION PTE LTD | Proposed Redecoration and Refurbishment Works to 55 Ayer Rajah Crescent | 2024-02-23 | S$4,940,827 |
| INTERLOCK SECURITY AND INVESTIGATION SERVICES PTE LTD | Engagement of Robotics Food Delivery Services | 2024-02-23 | S$32,000 |
| HWA AIK ENGINEERING PTE. LTD. | Proposed Demolition Works at 241 Jalan Ahmad Ibrahim | 2024-02-15 | S$298,000 |
| STEEL GIANT ENGINEERING PTE. LTD. | DESIGN & BUILD SHELTERED LINKWAY BETWEEN CLEANTECH TWO BLOCKS A & B @ CLEANTECH PARK | 2024-02-08 | S$325,888.88 |
| CPC CONSTRUCTION PTE. LTD. | Proposed Drain and Sewer Upgrading at Woodlands Road and Woodland Industrial Park D Street 2 | 2024-02-07 | S$20,500,888 |
| LANDSCAPE ENGINEERING PTE LTD | 2+1 Year Term Contract for Civil Engineering Works with Design and Authorities' Submission | 2024-02-06 | S$3 |
| JONES LANG LASALLE PROPERTY CONSULTANTS PTE LTD | APPOINTMENT OF FACILITY MANAGEMENT COMPANY FOR FACILITIES MAINTENANCE OF WEST DEPARTMENT 2 PROPERTIES AND ESTATE FOR A PERIOD OF 3 YEARS | 2024-02-05 | S$48,343,616.3 |
| C&W SERVICES (S) PTE. LTD. | APPOINTMENT OF A PANEL OF MARKETING AGENTS FOR JTC INDUSTRIAL AND COMMERCIAL SPACES | 2024-01-31 | S$1 |
| CBRE PTE. LTD. | APPOINTMENT OF A PANEL OF MARKETING AGENTS FOR JTC INDUSTRIAL AND COMMERCIAL SPACES | 2024-01-31 | S$2 |
| EDMUND TIE & COMPANY (SEA) PTE. LTD. | APPOINTMENT OF A PANEL OF MARKETING AGENTS FOR JTC INDUSTRIAL AND COMMERCIAL SPACES | 2024-01-31 | S$1 |
| ENGIE PROPERTY SERVICES PTE. LTD. | APPOINTMENT OF A PANEL OF MARKETING AGENTS FOR JTC INDUSTRIAL AND COMMERCIAL SPACES | 2024-01-31 | S$1 |
| HUTTONS ASIA PTE. LTD. Not yet published | APPOINTMENT OF A PANEL OF MARKETING AGENTS FOR JTC INDUSTRIAL AND COMMERCIAL SPACES | 2024-01-31 | S$1 |
| HPC BUILDERS PTE. LTD. | Construction Of 66KV Substation At Loyang Drive North | 2023-12-22 | S$29,520,000 |
| AEQON TJ PTE. LTD. | COMPREHENSIVE MAINTENANCE FOR NON-PROPRIETARY SYSTEMS AT JURONG ISLAND CHECKPOINT AND PULAU DAMAR LAUT CHECKPOINT FOR 24 MONTHS | 2023-12-21 | S$519,384 |
| NEO & GOH CONSTRUCTION PTE LTD | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Defu Estate, Kallang Way and Wilton Close | 2023-12-20 | S$3,168,000 |
| BENG SOON MACHINERY SERVICES (SINGAPORE) PTE LTD | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Defu Industrial Park (Batch 1) | 2023-12-19 | S$2,618,800 |
| ELEMENT GEOTECHNICAL TESTING (S) PTE. LTD. | Provision of Geotechnical Works Instrumentation and Monitoring Services for Drain and Sewer Upgrading at Woodlands Road and Woodlands Industrial Park D Street 2 | 2023-12-19 | S$106,320 |
| CPG CONSULTANTS PTE LTD | Provision of Civil and Structural Engineering Consultancy Services for Road Widening Works at AMK Industrial Park 2 | 2023-12-18 | S$235,431.48 |
| JONES LANG LASALLE PROPERTY CONSULTANTS PTE LTD | Appointment of Facility Management Company for Facilities Maintenance of East Department 1 Properties for a Period of 3 Years | 2023-12-11 | S$49,999,746.15 |
| GIMI INTERNATIONAL PTE. LTD. | PROVISION OF MANPOWER FOR VEGETATION CLEARING SERVICES TO FACILITATE LAND SURVEYING WORKS FOR JTC CORPORATION | 2023-12-06 | S$151,200 |
| JINYUE ALUMINIUM ENGINEERING (SINGAPORE) PTE. LTD. | Proposed Facade Repair and Rectification ("R&R") to Block 1 to 6 of Biopolis on Lot 04932W, 04929W & 04931M Mukim 3 at North Buona Vista Drive (Queenstown Planning Area) | 2023-12-04 | S$5,160,729 |
| LANDSCAPE ENGINEERING PTE LTD | Jurong Eco Garden Rejuvenation Works | 2023-11-29 | S$6,007,497 |
| WINSYS TECHNOLOGY PTE LTD | Design, Supply and Installation of BMS Interface Modules for BMS Integration to the Open Digital Platform(ODP) at JTC Properties | 2023-11-23 | S$152,259 |
| SURBANA JURONG CONSULTANTS PTE. LTD. | 2-Year Term Contract for Cadastral Surveys | 2023-11-21 | S$2 |
| UNITED SURVEYORS PTE LTD | 2-Year Term Contract for Cadastral Surveys | 2023-11-21 | S$1 |
| APBA TG HUMAN RESOURCE PTE. LTD. | Provision of a Panel of Resource Agencies to Supply IT Contract Resources for a Period of 3 Years | 2023-11-17 | S$1 |
| RMA CONSULTANTS PTE LTD | Provision of a Panel of Resource Agencies to Supply IT Contract Resources for a Period of 3 Years | 2023-11-17 | S$1 |
| OPTIMUM SOLUTIONS (SINGAPORE) PTE LTD | Provision of a Panel of Resource Agencies to Supply IT Contract Resources for a Period of 3 Years | 2023-11-17 | S$1 |
| ITCAN PTE. LIMITED | Provision of a Panel of Resource Agencies to Supply IT Contract Resources for a Period of 3 Years | 2023-11-17 | S$1 |
| BGC GROUP PTE. LTD. | Provision of a Panel of Resource Agencies to Supply IT Contract Resources for a Period of 3 Years | 2023-11-17 | S$1 |
| RIDIK PTE. LTD. Not yet published | Provision of a Panel of Resource Agencies to Supply IT Contract Resources for a Period of 3 Years | 2023-11-17 | S$1 |
| KELLER FOUNDATIONS (S E ASIA) PTE. LTD. | Design, Development and Build for Proposed Ground Improvement Works at Ayer Merbau Road, Jurong Island. | 2023-11-10 | S$5,788,000 |
| H3 ZOOM PTE. LTD. Not yet published | 1+1 Years Term Contract for Provision of Drone Service to Support Construction Site Visual Inspections (2023) | 2023-11-02 | S$129,600 |
| ESRI SINGAPORE PTE. LTD. | ENGAGEMENT OF APPLICATION MANAGED SERVICES (AMS) FOR GEOGRAPHIC INFORMATION SYSTEM (GIS) PLATFORMS IN JTC | 2023-10-31 | S$4,163,000 |
| C&W SERVICES (S) PTE. LTD. | Design, Development and Installation of New Chilled Water Plant Equipment at JTC Chemicals Hub | 2023-10-30 | S$977,700 |
| TSMP LAW CORPORATION Not yet published | Appointment of Law Firm(s) as Strategic Legal Partner for Advisory and Dispute Resolution Services for a period of two (2) years | 2023-10-25 | S$1 |
| RAJAH & TANN SINGAPORE LLP Not yet published | Appointment of Law Firm(s) as Strategic Legal Partner for Advisory and Dispute Resolution Services for a period of two (2) years | 2023-10-25 | S$1 |
| ACE PERIPHERALS PTE. LTD. Not yet published | 360 REALITY CAPTURE SAAS SOLUTION FOR 2 YEARS | 2023-10-20 | S$1,968,817.47 |
| EPIGRAM BOOKS PTE. LTD. Not yet published | 55 YEARS OF JTC INDUSTRIAL PLANNING AND ARCHITECTURE PUBLICATION | 2023-10-10 | S$354,800 |
| 3S COMMUNICATION PTE. LTD. | Supply, deliver, installation and commissioning of Video Conferencing and Audio-Visual equipment to boardroom, map room, lecture room and theatrette at JTC Summit, and training room T1C and theatrette at Jurong Town Hall | 2023-10-03 | S$195,525 |
| SURBANA JURONG INFRASTRUCTURE PTE. LTD. | SPECIALIST CONSULTANCY SERVICES FOR FEASIBILITY STUDY OF UNDERGROUND CAVERNS DEVELOPMENT AT GALI BATU | 2023-10-03 | S$2,355,000 |
| C&W SERVICES (S) PTE. LTD. | PROVISION OF RESOURCES FOR ENGAGEMENT WITH CUSTOMERS TO REGULARISE BREACHES IN JTC PROPERTIES FOR A PERIOD OF 3 YEARS | 2023-09-19 | S$3,080 |
| DELTEQ PTE LTD | PROCUREMENT OF HEWLETT PACKARD ENTERPRISE (HPE) SERVER UPGRADE | 2023-09-19 | S$81,999 |
| FONDA GLOBAL ENGINEERING PTE. LTD. | UPGRADING OF THE CLOSED-CIRCUIT TV SYSTEM FOR THE INLAND REVENUE AUTHORITY OF SINGAPORE | 2023-09-13 | S$349,241 |
| D' PERCEPTION SINGAPORE PTE. LTD. | DESIGN AND BUILD FOR RENOVATION OF NEW OFFICES AT LEVELS 3 AND 6 OF THE JTC SUMMIT | 2023-09-07 | S$1,035,506.34 |
| ENKON INTERNATIONAL CONSULTING ENGINEERS PTE LTD | Provision of Registered Inspector (Mechanical and Electrical) Services for JTC Integrated Business Park Development at Punggol Digital District | 2023-08-28 | S$32,550 |
| DHI WATER & ENVIRONMENT (S) PTE. LTD. | 2 + 2 Years Term Contract For Specialist Consultancy Services for the Environmental Monitoring & Management Plan in Singapore | 2023-08-14 | S$1 |
| CBRE GWS PTE. LTD. | Appointment of Facility Management Company for Facilities Maintenance of East Department 3, Central Department 2 and West Department 1n3 Properties for a Period of 3 Years | 2023-08-12 | S$71,232,263.54 |
| C&W SERVICES (S) PTE. LTD. | Appointment of Facility Management Company for Facilities Maintenance of East Department 3, Central Department 2 and West Department 1n3 Properties for a Period of 3 Years | 2023-08-12 | S$61,543,578.13 |
| HARFORD ENGINEERING PTE LTD | Proposed Enhancement Works at Ayer Rajah Precinct | 2023-08-08 | S$1,080,800 |
| HELM MARINE (SINGAPORE) PTE. LTD. Not yet published | Management Of JTC Sand Stockpile And Monitoring Of Sand Supply | 2023-08-04 | S$3,180,160 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Tuas and Defu Lane | 2023-07-26 | S$2,759,800 |
| ABL CONSULTANTS PTE. LTD. Not yet published | Provision of Multi-Disciplinary Consultancy Services for the Development of Heavy Vehicle Parking at JTC's New Estate | 2023-07-19 | S$482,000 |
| HUATIONG CONTRACTOR PTE LTD | Proposed Infrastructure Works at Loyang Drive (North) | 2023-07-07 | S$18,817,806 |
| HAO DA PTE LTD | Proposed Demolition Works at 6 Pasir Ris Farmway 1 and Substations | 2023-07-07 | S$2,769,555 |
| CHL CONSTRUCTION PTE LTD | A&A Works to Bedok Industrial Park E , Tampines Industrial Park A , Defu Industrial Estate and Kampong Ubi Industrial Estate | 2023-06-30 | S$5,130,836 |
| VIGCON CONSTRUCTION PTE LTD | A&A Works to Bedok Industrial Park E , Tampines Industrial Park A , Defu Industrial Estate and Kampong Ubi Industrial Estate | 2023-06-30 | S$13,543,468 |
| RECLAIMS ENTERPRISE PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Genting Lane, Kallang Way and Sungei Kadut | 2023-06-28 | S$1,668,649 |
| STARHUB LTD. | Leasing for WAN Connectivity and Hardware at Jurong Island Data Centre | 2023-06-21 | S$1,780,788.01 |
| DN HYBRID PTE. LTD. | REPAIRS AND REFURBISHMENT WORKS AT VARIOUS JTC INDUSTRIAL ESTATES AND COMPLEXES (GROUP 3) | 2023-06-19 | S$17,574,045 |
| PAL-LINK CONSTRUCTION PTE. LTD. | REPAIRS AND REFURBISHMENT WORKS AT VARIOUS JTC INDUSTRIAL ESTATES AND COMPLEXES (GROUP 3) | 2023-06-19 | S$9,451,948 |
| SHENGJIE ENGINEERING PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Sungei Kadut, Defu Lane and Tukang Estate | 2023-06-16 | S$2,200,000 |
| ANDERCO PTE. LTD. | Reinstatement Works to Factory Converted Dormitories (Batch 2) | 2023-06-14 | S$267,600 |
| MUTIARA (FE) PTE. LTD. | Reinstatement Works to Factory Converted Dormitories (Batch 2) | 2023-06-14 | S$11,202 |
| CH2M HILL SINGAPORE PRIVATE LIMITED | Feasibility Study For Siting New Wafer Fab Sites In JTC Industrial Estate On (I) Air Quality & Vibration, (II) Surface Runoff Quality Within Water Catchment Area, And (III) H&S Buffer To Sensitive Receptors | 2023-06-14 | S$665,798 |
| ACEPLP.COM PTE LTD Not yet published | 2-Year Term Contract for Provision of Integrated Digital Delivery (IDD) Managers for JTC's Building & Infrastructure Projects | 2023-06-12 | S$14,500 |
| SCHINDLER LIFTS (SINGAPORE) PTE. LTD. | PROPOSED LIFT REPLACEMENT / CONVERSION WITH 3 YEARS MAINTENANCE FOR JTC EXISTING BUILDING AT FUSIONOPOLIS 2, CHEMHUB AND OASIS @SAKRA | 2023-06-09 | S$7,272,000 |
| ENVIRONMENTAL RESOURCES MANAGEMENT (S) PTE LTD Not yet published | Study on Pollution Control of Waterfront Industrial Activities in Developed Countries | 2023-06-01 | S$395,000 |
| HARFORD ENGINEERING PTE LTD | CONSTRUCTION OF UTILITY SPECIFIC DUCTS AT TUAS WESTERN COAST | 2023-05-31 | S$5,428,977 |
| DHI WATER & ENVIRONMENT (S) PTE. LTD. | PROVISION OF CONSULTANCY SERVICES FOR ENVIRONMENTAL MONITORING AND MANAGEMENT PLAN (EMMP) FOR SITE CLEARANCE AND LAND PREPARATION WORKS OF PLOT A2 AT PASIR RIS WAFER FABRICATION PARK | 2023-05-29 | S$278,800 |
| MAXI MORRIE ENGINEERING PTE. LTD. | PROVISION OF TRAFFIC MANAGEMENT SYSTEM AT JURONG ISLAND CHECKPOINT | 2023-05-29 | S$1,739,000 |
| CBRE PTE. LTD. | Appointment of Panel of Valuers for the Provision of Valuation Services for JTC Corporation's Buyback of Industrial Properties for a Period of 3 Years | 2023-05-26 | S$1 |
| SAVILLS VALUATION AND PROFESSIONAL SERVICES (S) PTE. LTD. | Appointment of Panel of Valuers for the Provision of Valuation Services for JTC Corporation's Buyback of Industrial Properties for a Period of 3 Years | 2023-05-26 | S$1 |
| KNIGHT FRANK PTE LTD | Appointment of Panel of Valuers for the Provision of Valuation Services for JTC Corporation's Buyback of Industrial Properties for a Period of 3 Years | 2023-05-26 | S$1 |
| TONG SHING CONTRACTORS PRIVATE LIMITED | 1 + 1 YEAR TERM CONTRACT FOR RECTIFICATION WORKS TO EXISTING ROADS FOR HANDING OVER TO LTA | 2023-05-19 | S$2 |
| SWEE BUILDERS PTE LTD | 1 + 1 YEAR TERM CONTRACT FOR RECTIFICATION WORKS TO EXISTING ROADS FOR HANDING OVER TO LTA | 2023-05-19 | S$2 |
| CAST LABORATORIES PTE LTD | PROVISION OF INSTRUMENTATION AND MONITORING WORKS FOR PROPOSED OFF LOADING QUAY AT SERAYA, JURONG ISLAND | 2023-05-18 | S$68,800 |
| TANTRA INCORPORATED PTE. LTD. | APPOINTMENT OF EVENT ORGANISERS FOR RECREATION CENTRES: (I) CONCERTS AND CARNIVALS & (II) SPORTS TOURNAMENTS | 2023-05-09 | S$275,179 |
| KTC CIVIL ENGINEERING & CONSTRUCTION PTE LTD | DESIGN, DEVELOPMENT AND BUILD FOR PROPOSED TREE CLEARANCE AND LAND PREPARATION WORKS OF PLOT A2 AT PASIR RIS WAFER FABRICATION PARK | 2023-05-05 | S$6,312,000 |
| TRENDBUILD CONTRACTS PTE. LTD. | Conversion of Existing Meeting Room to Multimedia Video Conferencing Room on Level 10, The Treasury Building, Singapore 179434 | 2023-05-05 | S$223,815 |
| PDS INTERNATIONAL PTE LTD | 3-YEAR TERM CONTRACT FOR PROCUREMENT OF PERSONAL PROTECTIVE EQUIPMENT (PPE) [SAFETY BOOTS AND SAFETY EYEWEAR] FOR JTC | 2023-04-27 | S$1 |
| FLEMINGS SAFETY PTE. LTD. | 3-YEAR TERM CONTRACT FOR PROCUREMENT OF PERSONAL PROTECTIVE EQUIPMENT (PPE) [SAFETY BOOTS AND SAFETY EYEWEAR] FOR JTC | 2023-04-27 | S$1 |
| CLIMATE ASIA PTE. LTD. Not yet published | JTC Innovation Challenge 2022: Real time automated optimisation of air-conditioning system | 2023-04-27 | S$250,000 |
| YENG TONG CONSTRUCTION PTE LTD | Removal and Disposal of a Single Buoy Mooring (SBM) System at Sakra, Jurong Island | 2023-04-17 | S$81,000 |
| QXY RESOURCES PTE. LTD. | REPAIR & REFURBISHMENT WORKS AT VARIOUS JTC INDUSTRIAL ESTATES (GROUP 1B) | 2023-04-17 | S$19,470,400 |
| CHIONG CONSTRUCTION PTE. LTD. | REPAIR & REFURBISHMENT WORKS AT VARIOUS JTC INDUSTRIAL ESTATES (GROUP 1B) | 2023-04-17 | S$4,087,885 |
| EASE SOLUTIONS PTE. LTD. Not yet published | Provision of Software Licenses Maintenance for JIRA Service Management and Plugins for JTC Corporation | 2023-04-14 | S$102,987.35 |
| ANTARA KOH PRIVATE LIMITED | DESIGN AND BUILD OF OFF-LOADING QUAY AT SERAYA, JURONG ISLAND | 2023-04-06 | S$4,307,080 |
| SPTEL PTE. LTD. Not yet published | PROCUREMENT OF NETWORK CONNECTIVITY FOR INTERNET ACCESS AND DISASTER RECOVERY | 2023-04-06 | S$223,302 |
| SMM PTE. LTD. | 2-YEAR TERM CONTRACT FOR RESIDENT SITE SUPERVISORS FOR JTC'S BUILDING AND INFRASTRUCTURE PROJECTS (YEAR 2023 to 2025) | 2023-03-31 | S$99,400 |
| QBE INSURANCE (SINGAPORE) PTE. LTD. | PLACEMENT OF INSURANCE POLICIES FOR JTC'S CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS | 2023-03-30 | S$1 |
| SOMPO INSURANCE SINGAPORE PTE. LTD. | PLACEMENT OF INSURANCE POLICIES FOR JTC'S CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS | 2023-03-30 | S$1 |
| MS FIRST CAPITAL INSURANCE LIMITED | PLACEMENT OF INSURANCE POLICIES FOR JTC'S CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS | 2023-03-30 | S$1 |
| ZURICH INSURANCE COMPANY LTD (Singapore Branch) Not yet published | PLACEMENT OF INSURANCE POLICIES FOR JTC'S CORPORATE INSURANCE PROGRAMME FOR A PERIOD OF 2 YEARS | 2023-03-30 | S$1 |
| ARCHITECTS TEAM 3 PTE. LTD. | PROVISION OF MULTI-DISCIPLINARY CONSULTANCY SERVICES FOR ADDITIONS & ALTERATIONS OF PENJURU RECREATION CENTRE AT 27 PENJURU WALK | 2023-03-14 | S$7.5 |
| SMM PTE. LTD. | Appointment of Facilities Management Company for Facilities Maintenance of Land-based Properties for a Period of 3 years | 2023-02-24 | S$34,905,825 |
| AIK LEONG PLUMBING CONSTRUCTION PTE LTD | Sewer Upgrading at Tuas-Pioneer Industrial Estate | 2023-02-15 | S$28,108,000 |
| RSP ARCHITECTS PLANNERS & ENGINEERS (PTE) LTD | Provision Of Multi-Disciplinary Consultancy Services for The Proposed Addition and Alteration (A&A) Works for Block 28 Ayer Rajah Crescent | 2023-02-01 | S$5.68 |
| AECOM SINGAPORE PTE. LTD. | Provision of Specialist Consultancy Services for Environmental Impact Assessment (EIA) Studies at Tengah Heavy Vehicle Parking (HVP), Cleantech Park (CTP) and Bahar Estate | 2022-12-29 | S$912,800 |
| DHI WATER & ENVIRONMENT (S) PTE. LTD. | Provision of Specialist Consultancy Services for Environmental Impact Assessment (EIA) Studies at Tengah Heavy Vehicle Parking (HVP), Cleantech Park (CTP) and Bahar Estate | 2022-12-29 | S$176,990 |
| ENTIIS PTE. LTD. | Procurement of privilege activity recording system (ObserveIT) software licensing support and maintenance for 2 years | 2022-12-29 | S$136,326.92 |
| IZENO PRIVATE LIMITED | Provision of Software License Maintenance for JTC DATAHUB | 2022-12-27 | S$1,093,541.5 |
| ERNST & YOUNG ADVISORY PTE. LTD. | Consultancy Services for Manpower Resource Optimisation | 2022-12-19 | S$600,000 |
| STARHUB LTD. | Nominated Sub-Contract for Information Communication Technology (ICT) Systems at Integrated Business Park Development on CC1, CC2 and CC3 at Punggol Digital District | 2022-12-05 | S$7,986,678 |
| CAPGEMINI SINGAPORE PTE. LTD. | Engagement of Services for the Research and Consultancy, System Development, Implementation, and Application Maintenance Services of Customer Service Portal (CSP) | 2022-11-28 | S$6,886,350 |
| ABSOLUT OUTDOORS PTE. LTD. | SUPPLY AND INSTALLATION OF PARASOLS AND PICNIC BENCHES FOR JTC RECREATION CENTRES | 2022-11-11 | S$310,308 |
| ADSAN LAW LLC Not yet published | APPOINTMENT OF LAW FIRM(S) AS STRATEGIC LEGAL PARTNER FOR ARREARS MANAGEMENT SERVICES FOR A PERIOD OF THREE (3) YEARS | 2022-11-04 | S$1 |
| SAVILLS PROPERTY MANAGEMENT PTE. LTD. | APPOINTMENT OF MANAGING AGENT FOR VARIOUS ESTATES UNDER EAST DIVISION | 2022-10-21 | S$1,457,280 |
| SH INTEGRATED SERVICES PTE. LTD. | Penjuru Recreation Centre - Synthetic Field Returfing, Installation of New Lightings and Resurfacing of Courtyard | 2022-10-21 | S$1,388,000 |
| RECLAIMS ENTERPRISE PTE. LTD. | Proposed Demolition Works at 47A Jalan Buroh | 2022-10-21 | S$188,000 |
| WSH EXPERTS PTE. LTD. Not yet published | 2 YEARS TERM CONTRACT FOR PROVISION OF CONTRACTS OFFICERS | 2022-10-14 | S$5,120 |
| CHARTWORTH ENTERPRISE SINGAPORE PTE. LTD. | Proposed Site Clearance at Woodlands Wafer Fab Park | 2022-10-04 | S$5,524,020 |
| QXY RESOURCES PTE. LTD. | Reinstatement & Refurbishment (R&R) of Black and White Walk-ups and Semi-detach Houses in Wessex | 2022-09-30 | S$15,300,000 |
| FLEMINGS SAFETY PTE. LTD. | 3-YEAR TERM CONTRACT FOR PROCUREMENT OF PERSONAL PROTECTIVE EQUIPMENT (PPE) [SAFETY BOOTS, SAFETY EYEWEAR, LONG SLEEVE TOP] FOR JTC STAFFS ENTERING CONSTRUCTION WORKSITES AND FACILITIES & ESTATES | 2022-09-26 | S$1 |
| GREENSAFE INTERNATIONAL PTE. LTD. | 2 Year Term Contract for Provision of Workplace Safety and Health Managers | 2022-09-22 | S$20,750 |
| CAPGEMINI SINGAPORE PTE. LTD. | ENGAGEMENT OF SERVICES FOR REQUIREMENT STUDY, DESIGN, DEVELOPMENT, TESTING AND IMPLEMENTATION OF GIS PLATFORM ON GCC ENVIRONMENT | 2022-09-20 | S$845,320 |
| ENVIROSOLUTIONS & CONSULTING PTE. LTD. | PROVISION OF AIR QUALITY MONITORING SERVICES AT WOODLANDS WAFER FAB PARK AND NORTH COAST WAFER FAB PARK | 2022-09-19 | S$303,000 |
| MS FIRST CAPITAL INSURANCE LIMITED | PLACEMENT OF INSURANCE POLICIES FOR THE OPERATION OF JURONG ROCK CAVERNS FOR A PERIOD OF ONE YEAR | 2022-08-31 | S$1 |
| PROPELL INTEGRATED PTE LTD | 12 MONTHS TERM CONTRACT FOR LICENSING AND SERVICING OF ELECTRICAL INSTALLATION AT VARIOUS JTC INDUSTRIAL ESTATES | 2022-08-24 | S$452,514 |
| HWA AIK ENGINEERING PTE. LTD. | Proposed Demolition Works at 1 Pasir Ris Coast Industrial Park 1, 70 Pasir Ris Farmway 1, 63 Pasir Ris Farmway 3 and Substation | 2022-08-16 | S$1,858,000 |
| CPG FACILITIES MANAGEMENT PTE LTD | 24/7 CALL CENTER OPERATION FOR JTC ESSENTIAL SERVICES CENTRE | 2022-08-15 | S$98,126 |
| HOWDEN INSURANCE BROKERS (S.) PTE. LIMITED | Appointment of Insurance Broker for a Period of 3 Years | 2022-07-29 | S$2 |
| CH2M HILL SINGAPORE PRIVATE LIMITED | Multi-Disciplinary Consultancy Services for the Site Specific Engineering Study for Climate Change Adaptation Planning for Jurong Island | 2022-07-29 | S$10,314,861.2 |
| MEINHARDT (SINGAPORE) PTE LTD | Provision of Accredited Checking Organisation and Accredited Checker(Geotechnical) Services for Construction of Infrastructure Works at Bulim (Phase 2) | 2022-07-28 | S$668,500 |
| HY M&E CONSULTANCY SERVICES PTE. LTD. | PROVISION OF EARTHING SPECIALIST CONSULTANCY SERVICES FOR PROPOSED 66kV SUBSTATION AT LOYANG DRIVE NORTH | 2022-07-22 | S$45,000 |
| HWA AIK ENGINEERING PTE. LTD. | Proposed Demolition of Existing Factory Buildings and Ancillary Structures at Sungei Kadut, Kranji Loop and Defu Lane | 2022-07-21 | S$1,787,000 |
| OGP KONSULT PTE. LTD. Not yet published | MULTI-DISCIPLINARY CONSULTANCY SERVICES FOR PROPOSED REPAIRS AND REFURBISHMENT WORKS AT JURONG ISLAND (JI) CHECKPOINT, JURONG PIER ROAD JETTY AND ACCESS ROADS TO PULAU DAMAR LAUT (PDL) | 2022-07-21 | S$196,008.35 |
| CTM FACILITIES MANAGEMENT PTE. LTD. | APPOINTMENT OF FACILITY MANAGEMENT COMPANY FOR THE PROVISION OF FACILITIES MAINTENANCE SERVICES TO COCHRANE RECREATION CENTRE FOR A PERIOD OF 2 YEARS & 7 MONTHS | 2022-07-19 | S$2,710,769.9 |
| AIK SUN DEMOLITION & ENGINEERING PTE LTD | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$1 |
| HAO DA PTE LTD | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$0.01 |
| NEO & GOH CONSTRUCTION PTE LTD | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$0.1 |
| BENG SOON MACHINERY SERVICES (SINGAPORE) PTE LTD | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$1 |
| AIK LEONG PLUMBING CONSTRUCTION PTE LTD | Sewer Upgrading at Benoi-Gul Industrial Estate | 2022-07-14 | S$22,490,000 |
| HWA AIK ENGINEERING PTE. LTD. | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$1 |
| PENG CHUAN ENGINEERING CONSTRUCTION PTE. LTD. | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$1 |
| RECLAIMS ENTERPRISE PTE. LTD. | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$1 |
| SHENGJIE ENGINEERING PTE. LTD. | Prequalification of Contractors for Listing on JTC's Panel of Demolition Contractors for a Period of 3 Years | 2022-07-14 | S$0.01 |
| MAO SHENG QUANJI CONSTRUCTION PTE LTD | TERM CONTRACT FOR ARBORICULTURE, HORTICULTURE & TURF WORKS MAINTENANCE TO JTC PROPERTIES AND LAND (EAST) FOR A PERIOD OF 1 YEAR | 2022-07-13 | S$351,600 |
| KJS CONSTRUCTION PTE LTD | PROPOSED REPAIR & REFURBISHMENT WORKS AT TOA PAYOH INDUSTRIAL PARK | 2022-07-13 | S$7,868,443 |
| TUAS POWER LTD | Jurong Island Renewable Energy Request for Proposal | 2022-07-13 | S$2,144,274 |
| KEPPEL ENERGY NEXUS PTE. LTD. | Jurong Island Renewable Energy Request for Proposal | 2022-07-13 | S$900,000 |
| VFLOWTECH PTE. LTD. Not yet published | Jurong Island Renewable Energy Request for Proposal | 2022-07-13 | S$2,096,300 |
| JONES LANG LASALLE PROPERTY CONSULTANTS PTE LTD | Appointment of Facilities Management Company for Facilities Maintenance of East Department 2 Properties for a Period of 3 Years | 2022-07-08 | S$37,027,684.5 |
| FUJIFILM BUSINESS INNOVATION SINGAPORE PTE. LTD. | Engagement of Services for the Implementation and Maintenance of Secure Electronic Signature (SES) Digital Signature System | 2022-06-21 | S$357,812 |
| DHI WATER & ENVIRONMENT (S) PTE. LTD. | Specialist Consultancy Services for Environmental Impact Studies at Woodlands North Coast (WNC) | 2022-06-16 | S$435,500 |
| TUV SUD PSB PTE. LTD. | Appointment of Specialist Professional Engineer(s) to Perform Inspections for Lifts in all JTC Properties | 2022-06-15 | S$1 |
| TONG SHING CONTRACTORS PRIVATE LIMITED | 2+1 Year Term Contract for Minor Civil Engineering Works | 2022-06-13 | S$3 |
| SWEE BUILDERS PTE LTD | 2+1 Year Term Contract for Minor Civil Engineering Works | 2022-06-13 | S$3 |
| FREIGHT LINKS EXPRESS ARCHIVERS PTE LTD | 2-Year Term Contract for the Provision of Storage and Records Management Services | 2022-06-09 | S$144,000 |
| KJS CONSTRUCTION PTE LTD | Proposed Additions & Alterations to Eating House at 71 Tuas Avenue 1 | 2022-06-02 | S$886,976 |
| ZARCH COLLABORATIVES PTE. LTD. Not yet published | Provision Of Multi-Disciplinary Consultancy Services For The Regularisation Of Fire Safety Works (R&R) To Existing Fusionopolis 1 Building | 2022-06-02 | S$8.8 |
| BSG LANDSCAPE & CONSTRUCTION PTE. LTD. | 2-YEAR TERM CONTRACT FOR PROVISION OF HORTICULTURE SERVICES AT JURONG ISLAND CHECKPOINT | 2022-06-01 | S$47,030 |
| DING SHENG ENGINEERING PTE LTD | PROPOSED REINSTATEMENT OF VACANT UNIT AT BLK 16 DEFU LANE 10 #01-374 AND REPAIR/STRENGTHEN THE EXISTING STRUCTURE FOR BOTH UNITS #01-372 (OCCUPIED UNIT) AND #01-374 AND PROPOSED RECONSTRUCTION AND REPAIR WORKS TO BLK 1081 EUNOS AVE 7 FIRE AFFECTED UNIT #01-170 & #01-172 | 2022-05-23 | S$651,380 |
| SOIL INVESTIGATION PTE. LIMITED | 2-Year Term Contract for Geophysical and Survey Works for JTC Estates | 2022-05-13 | S$1 |
| RYOBI GEOTECHNIQUE INTERNATIONAL PTE. LTD. | 2-Year Term Contract for Geophysical and Survey Works for JTC Estates | 2022-05-13 | S$1 |
| TALOGY (SINGAPORE) PTE. LTD. | Provision of Psychometric Assessments for a Period of 2 Years | 2022-05-10 | S$40,000 |
| EASE SOLUTIONS PTE. LTD. Not yet published | Provision of Software Licenses Maintenance for JIRA Service Management and Plugins for JTC Corporation | 2022-04-29 | S$110,534.12 |
| GOH SIN GUAN HUAT PTE LTD | Proposed Infrastructure Works at Tuas South Coast and Tuas South View Avenue 14 Extension | 2022-04-11 | S$18,888,000 |
| AECOM SINGAPORE PTE. LTD. | PROVISION OF CONSULTANCY SERVICES FOR RECLAMATION AT LORONG HALUS | 2022-04-06 | S$2,750,000 |
| AECOM SINGAPORE PTE. LTD. | 24 MONTHS TERM CONTRACT FOR PROVISION OF ENVIRONMENTAL ADVISORY SERVICES (YEAR 2022) | 2022-04-05 | S$426,500 |
| BETH-EL (ASIA PACIFIC) PTE. LTD. | Provision of Security & Blast Consultancy Services for 66kV Substation at Loyang Drive North | 2022-03-31 | S$160,000 |
| HCL SINGAPORE PTE. LTD. | Engagement of Services for the System Development, Implementation, and Application Maintenance Services of ATLAS for JTC | 2022-03-31 | S$3,430,011 |
| KHIM SEAH ENTERPRISE PTE. LTD. | 1-Year Term Contract for the Provision of Shuttle Bus Services at International Business Park | 2022-03-22 | S$110,250 |
| EPIGRAM BOOKS PTE. LTD. Not yet published | Provision of Design Services, Publication and Production of JTC55 Commemorative Book | 2022-03-21 | S$226,000 |
| PROSEGUR SINGAPORE PTE. LTD. | Provision of Unarmed Security Manpower Services and Systems at Jurong Island for a Period of 5 Years | 2022-03-17 | S$38,825,507 |
| AETOS SECURITY MANAGEMENT PTE. LTD. | Provision of Armed Security Manpower Services at Jurong Island for a period of 5 years | 2022-03-17 | S$37,030,980 |
| YJP SURVEYORS PTE LTD | 3-Year Term Contract for Engineering Surveys | 2022-03-15 | S$2 |
| CAK & FG SURVEY PTE. LTD. | 3-Year Term Contract for Engineering Surveys | 2022-03-15 | S$1 |
| SIEMENS PTE. LTD. | NSC for Building Management System at Integrated Business Park Development on CC1, CC2 and CC3 at PDD | 2022-03-10 | S$4,131,109 |
| C&W SERVICES (S) PTE. LTD. | Appointment of Facilities Management Company for Facilities Maintenance of Central Department 1 Properties for a Period of 3 Years | 2022-02-09 | S$62,505,135.22 |
| ENSIGN INFOSECURITY (SMARTTECH) PTE. LTD. | Engagement of services for the provision of vulnerability and compliance management solution for JTC for 3 years | 2022-01-28 | S$477,880 |
| ABL CONSULTANTS PTE. LTD. Not yet published | Provision of Single Disciplinary Consultancy Services (Civil & Structural Engineering) for Land Preparation and Infrastructure Works at Woodlands Wafer Fabrication Park (WFP) | 2022-01-28 | S$3.6 |
| AECOM SINGAPORE PTE. LTD. | Provision of Professional Engineering Services to conduct Landfill Gas Study And Sampling Study at Lorong Halus | 2022-01-26 | S$335,000 |
| FUJITSU ASIA PTE LTD | ENGAGEMENT OF SERVICES FOR THE SUPPLY, MIGRATION, IMPLEMENTATION AND APPLICATION MANAGEMENT SERVICES OF DOCUMENT MANAGEMENT SYSTEM 2.0 (DMS 2.0) FOR JTC | 2022-01-25 | S$4,794,669 |
| AQUAFORCE PRIVATE LIMITED | 18 MONTHS TERM CONTRACT FOR MAINTENANCE OF WATER PUMPING SYSTEM, POTABLE WATER SERVICE INSTALLATION AND WATER TANK CLEANING AT VARIOUS JTC INDUSTRIAL ESTATES | 2022-01-14 | S$243,252.5 |
| MOTT MACDONALD SINGAPORE PTE LIMITED | PROVISION OF ENVIRONMENTAL SUSTAINABLE DESIGN (ESD) CONSULTANCY SERVICES FOR WIND DRIVEN RAIN (WDR) SIMULATION AND FACADE TYPOLOGIES STUDIES FOR JTC DEVELOPMENTS | 2022-01-10 | S$298,000 |
| CPG CONSULTANTS PTE LTD | JTC's TERM CONTRACT TENDER FOR RENDERING OF TRAFFIC AND TRANSPORT CONSULTANCY SERVICES FOR A PERIOD OF 2 YEARS | 2022-01-06 | S$3 |
| IZENO PRIVATE LIMITED | Provision of Software License Maintenance for JTC Datahub | 2021-12-30 | S$347,173.02 |
| FONG CONSULT PTE. LTD. Not yet published | PERIODIC STRUCTURAL INSPECTION AT VARIOUS JTC PROPERTIES | 2021-12-21 | S$239,400 |
| STERLING ENGINEERS PTE. LTD. Not yet published | PERIODIC STRUCTURAL INSPECTION AT VARIOUS JTC PROPERTIES | 2021-12-21 | S$39,100 |
| NCS PTE. LTD. | SUPPLY, DELIVERY AND MAINTENANCE OF WEBPAGE DEFACEMENT DETECTION AND AUTO-REPLACEMENT SOLUTION ON GCC | 2021-12-17 | S$223,753 |
| CBRE GWS PTE. LTD. | APPOINTMENT OF FACILITY MANAGEMENT COMPANY FOR FACILITIES MAINTENANCE OF CENTRAL DEPARTMENT 3 PROPERTIES FOR A PERIOD OF 3 YEARS | 2021-12-03 | S$31,333,826.81 |
| O'CONNOR'S SINGAPORE PTE LTD | Nominated Sub-Contract for Integrated Security Management System at Integrated Business Park Development on CC1, CC2 and CC3 at Punggol Digital District | 2021-11-17 | S$2,736,663 |
| KJS CONSTRUCTION PTE LTD | TERM CONTRACTS FOR FACTORY UNIT REINSTATEMENT WORKS AT VARIOUS JTC INDUSTRIAL PROPERTIES UNDER CENTRAL & EAST ZONES FOR ONE YEAR | 2021-11-09 | S$1 |
| ESPIRIT BUILDING & ENGINEERING PTE. LTD. | TERM CONTRACTS FOR FACTORY UNIT REINSTATEMENT WORKS AT VARIOUS JTC INDUSTRIAL PROPERTIES UNDER CENTRAL & EAST ZONES FOR ONE YEAR | 2021-11-09 | S$1 |
| TOKIO MARINE INSURANCE SINGAPORE LTD. | Insurance Contracts for JTC's Work Injury Compensation, Group Personal Accident and Group Term Life Insurance Programme for a Period of 2 years | 2021-10-28 | S$1 |
| SINGAPORE LIFE LTD. | Insurance Contracts for JTC's Work Injury Compensation, Group Personal Accident and Group Term Life Insurance Programme for a Period of 2 years | 2021-10-28 | S$1 |
| ZURICH INSURANCE COMPANY LTD (Singapore Branch) Not yet published | Insurance Contracts for JTC's Work Injury Compensation, Group Personal Accident and Group Term Life Insurance Programme for a Period of 2 years | 2021-10-28 | S$1 |
| WSH EXPERTS PTE. LTD. Not yet published | PROVISION OF MANPOWER FOR VEGETATION CLEARING SERVICES TO FACILITATE LAND SURVEYING WORKS FOR JTC CORPORATION | 2021-10-28 | S$169,200 |
| CONCORDE SECURITY PTE. LTD. | Provision of Security Manpower Services for JTC Properties at Eastern Part of Singapore | 2021-10-27 | S$547,650 |
| 800 SUPER WASTE MANAGEMENT PTE LTD | 2-YEAR TERM CONTRACT FOR CLEANING AND CONSERVANCY SERVICES AT VARIOUS JTC INDUSTRIAL ESTATES INCLUDING VACANT LANDS AND ROADS | 2021-10-11 | S$6,202,302 |
| LS 2 SERVICES PTE LTD | 2-YEAR TERM CONTRACT FOR CLEANING AND CONSERVANCY SERVICES AT VARIOUS JTC INDUSTRIAL ESTATES INCLUDING VACANT LANDS AND ROADS | 2021-10-11 | S$11,388,000 |
| KPMG SERVICES PTE. LTD. | Provision of Internal Audit Services for 3 Years | 2021-10-01 | S$505,500 |
| GEONAMICS (S) PTE LTD | Soil Investigation and Survey works at Lorong Halus (along Serangoon Harbour) | 2021-09-28 | S$1,939,677.5 |
| DHI WATER & ENVIRONMENT (S) PTE. LTD. | MARINE ENVIRONMENTAL IMPACT ASSESSMENT AND SHIP HANDLING STUDY AT LORONG HALUS | 2021-09-28 | S$1,998,888 |
| KPMG SERVICES PTE. LTD. | JTC Innovation Challenge - Phase 1: Automation and Productivity | 2021-09-27 | S$245,780 |
| SMM PTE. LTD. | Reinstatement Works to Factory Converted Dormitories | 2021-09-13 | S$266,500 |
| ACEPROJECT CONSTRUCTION PTE. LTD. | Reinstatement Works to Factory Converted Dormitories | 2021-09-13 | S$258,861 |
| HD CONTRACTOR PTE. LTD. | PROPOSED REPAIRS AND REFURBISHMENT WORKS TO TERRACE WORKSHOPS AT TOA PAYOH INDUSTRIAL PARK BLOCK 11, INCLUDING BACKYARD RECONSTRUCTION | 2021-09-09 | S$1,912,827 |
| NATIONAL UNIVERSITY OF SINGAPORE Not yet published | JTC innovation Challenge - Phase 3: Sustainability And Resilience | 2021-08-31 | S$229,358.4 |
| SINGAPORE INSTITUTE OF TECHNOLOGY Not yet published | JTC innovation Challenge - Phase 3: Sustainability And Resilience | 2021-08-31 | S$245,160 |
| AEQON TJ PTE. LTD. | 2-YEAR TERM CONTRACT FOR COMPREHENSIVE MAINTENANCE OF NON-PROPRIETARY SECURITY SYSTEMS AT JURONG ISLAND CHECKPOINT AND PULAU DAMAR LAUT CHECKPOINT | 2021-08-26 | S$539,400 |
| KPMG SERVICES PTE. LTD. | Engagement of Consultancy Services for Finance Data Analytics | 2021-08-06 | S$100,000 |
| QXY RESOURCES PTE. LTD. | PROPOSED REPAIR & REDECORATION WORKS AT BEDOK INDUSTRIAL ESTATE | 2021-07-28 | S$27,517,400 |
| CBRE GWS PTE. LTD. | Appointment of FMC to provide Start-up Operations and Maintenance Services for new developments for a period of 3 years | 2021-07-23 | S$9,282,781.65 |
| NCS PTE. LTD. | Provision of Maintenance Contract for IT Equipment | 2021-07-21 | S$2,911,632 |
| INTEGRATED HEALTH PLANS PTE LTD | PROVISION OF MANAGED MEDICAL HEALTHCARE SERVICE TO JTC CORPORATION | 2021-07-15 | S$1 |
| NCS PTE. LTD. | Provision of VMWARE Licenses renewal and support services | 2021-07-14 | S$726,665 |
| WIPRO NETWORKS PTE. LIMITED | APPLICATION MANAGEMENT SERVICES FOR DOCUMENT MANAGEMENT SYSTEM (DMS) FOR JTC | 2021-07-13 | S$910,000 |
| CHINA STATE CONSTRUCTION ENGINEERING CORPORATION LIMITED Singapore Branch | PROPOSED CONSTRUCTION OF (A) DLN RAMP AND ASSOCIATED FACILITY BUILDINGS AND (B) ROAD TUNNEL LINKING BAHAR TO BULIM (PART 1) | 2021-07-09 | S$135,000,000 |
| EQUATION TECHNOLOGY & CABLING PTE LTD | NOMINATED SUB-CONTRACT FOR STRUCTURED CABLING SYSTEM AT INTEGRATED BUSINESS PARK DEVELOPMENT ON CC1, CC2 AND CC3 AT PUNGGOL DIGITAL DISTRICT | 2021-07-02 | S$2,305,748.04 |
| JMJ ASSOCIATES ASIA PACIFIC (PTE.) LTD. Not yet published | PROVISION OF CONSULTANCY SERVICE TO BUILD WORKPLACE SAFETY AND HEALTH CULTURE FOR JTC CONSTRUCTION PROJECTS | 2021-06-23 | S$435,000 |
| MANPOWER STAFFING SERVICES (SINGAPORE) PTE LTD | Appointment of a Panel of Recruitment Agencies to provide Contingent Search Services to fill JTC Employee Positions for a Period of 2 Years | 2021-06-09 | S$1 |
| RMA CONSULTANTS PTE LTD | Appointment of a Panel of Recruitment Agencies to provide Contingent Search Services to fill JTC Employee Positions for a Period of 2 Years | 2021-06-09 | S$1 |
| EPS CONSULTANTS PTE LTD Not yet published | Appointment of a Panel of Recruitment Agencies to provide Contingent Search Services to fill JTC Employee Positions for a Period of 2 Years | 2021-06-09 | S$1 |
| GOOD JOB CREATIONS (SINGAPORE) PTE. LTD. Not yet published | Appointment of a Panel of Recruitment Agencies to provide Contingent Search Services to fill JTC Employee Positions for a Period of 2 Years | 2021-06-09 | S$1 |
| RGF TALENT SOLUTIONS SINGAPORE PTE. LTD. Not yet published | Appointment of a Panel of Recruitment Agencies to provide Contingent Search Services to fill JTC Employee Positions for a Period of 2 Years | 2021-06-09 | S$1 |
| GLOBAL SEARCH PARTNERS PTE. LTD. Not yet published | Appointment of a Panel of Recruitment Agencies to provide Contingent Search Services to fill JTC Employee Positions for a Period of 2 Years | 2021-06-09 | S$1 |
| DIGI ENGINEERING PTE. LTD. | TWO (2) YEARS TERM CONTRACT FOR MAINTENANCE OF FIRE PROTECTION SYSTEMS AT JTC PROPERTIES | 2021-05-25 | S$373,773 |
| OES TECHNOLOGY PTE. LTD. | Provision of Facial Recognition Access Control with 2 Years Maintenance at JTC Summit | 2021-05-21 | S$179,400 |
| AEDGE HOLDINGS PTE. LTD. | 2-YEAR TERM CONTRACT FOR THE PROVISION OF SHUTTLE BUS SERVICE AT SELETAR AEROSPACE PARK AND CLEANTECH PARK | 2021-05-19 | S$591,888 |
| RHYTHME TECHNOLOGY PTE LTD | TWO (2) YEARS TERM CONTRACT FOR MAINTENANCE OF FIRE PROTECTION SYSTEMS AT AMK AUTOPOINT, AMK TECH 2, AMK TECHLINK, YS-ONE AND SIN MING AUTOCARE | 2021-05-18 | S$487,680 |
| BAN CHON CORPORATION & TRADING PTE LTD | Construction of Roads, Drains, Sewers and Ancillary Works at Tuas link 4 / Tuas Link Drive | 2021-05-18 | S$4,798,000 |
| RYOBI GEOTECHNIQUE INTERNATIONAL PTE. LTD. | PROPOSED INSTRUMENTATION AND MONITORING WORKS FOR (A) DLN RAMP AND ASSOCIATED FACILITY BUILDINGS AND (B) ROAD TUNNEL LINKING BAHAR TO BULIM (PART 1) | 2021-04-27 | S$557,000 |
| CUSHMAN & WAKEFIELD VHS PTE. LTD. Not yet published | ENGAGEMENT OF CONSULTANCY SERVICES FOR INTERNATIONAL INDUSTRIAL LAND BENCHMARKING STUDY | 2021-04-27 | S$1 |
| MAXI MORRIE ENGINEERING PTE. LTD. | PROVISION OF AUTOMATED BARRIER SYSTEM AT JURONG ISLAND CHECKPOINT | 2021-04-26 | S$431,836 |
| ST ENGINEERING CLOUD AND DATA CENTRE SOLUTIONS PTE. LTD. | Design, Development And Fit Out Proposed Data Centre With 5 + 5 Years Maintenance At No. 81 Jurong Island Highway | 2021-04-13 | S$6,552,775 |
Contains information from ACRA Information on Corporate Entities accessed on 2026-09-16 from data.gov.sg, made available under the terms of the Singapore Open Data Licence version 1.0. Government tender data from GeBIZ Government Procurement, same licence.Sole proprietorships, partnerships and entities whose registered particulars would identify a natural person are not listed — see data sources & methodology.
Not an official business register. For official records use bizfile.gov.sg.
Spotted an error, or want a company removed? Use the contact form — no justification required for removal.